DOME Construction Progress
2025
June 2025 — Present
Hatch Installation
April 2025 — Present
Ice Shelters
April 2025 — Present
DOME Facility Equipment
2024
November 2024 — April 2025
Underground Piping and Yard Excavation
August 2024 — June 2025
Penetration Fabrication at Peterson
July 2024 — June 2025
Fabrication of Equipment Hatch
April 2024 — Present
Equipment Pad
April 2024 — July 2025
DOME Penetrations
March 2024 — Present
DOME Demolition
January 2024 — April 2024
Retaining Wall
2023
December 2023 — Present
Control Room
October 2023